Office Relocation Checklist: 8 Weeks to Move Day

What to book, count, and confirm so the business opens on time at the new address

Share This Article
Commercial Moving Article 2026-06-16 Updated 8 min read

Office Relocation Checklist for Toronto Businesses: 8 Weeks to Move Day | G&T Moving Blog

To prepare for an office move in Toronto, start about eight weeks out: confirm the building rules at both addresses, get an exact item count or a site visit from your mover, decide who handles IT and furniture installation, and book the dock and service elevator before you lock the date. Everything else on this checklist follows from those four things.

We plan office and commercial moves across Toronto and the GTA, and the jobs that go wrong rarely go wrong on the truck. They go wrong earlier, when a count was guessed, a certificate of insurance was requested the morning of the move, or nobody owned the question of who reconnects the computers. This checklist is ordered so those decisions get made while there is still time to change them.

Key Takeaways

  • Eight weeks out: pick one internal move coordinator, get both buildings’ move rules in writing, and ask your mover for a site visit.
  • Six weeks out: decide what moves, what is disposed of, and what needs temporary storage. Order any new racking now — it typically needs about a month.
  • Four weeks out: book the service elevator and loading dock at both ends, and send the certificate of insurance wording to your mover.
  • Two weeks out: label every desk, cabinet, and machine with a colour or zone code matched to the new floor plan.
  • Move night: one person from your side with authority to make calls, and a mover whose lead is reachable by phone the whole time.

The Same Office, Before and After

Workstations as we found them, furniture staged by destination zone, chairs wrapped individually, and reception back in service at the new address.

Open plan office with workstations and task chairs before a Toronto office relocation
Before: the floor as we found it.
Office desks, cartons and lockers staged along a corridor ready for loading
Staged by destination room before anything leaves the floor.
Office chairs individually wrapped in plastic film and lined up before an office move
Task chairs wrapped individually before they leave the floor.
Finished office reception desk and lobby after the relocation was completed
After: reception in place at the new address.

8 weeks out: set the frame

Name one person inside the company who owns the move. Not a committee: one coordinator who answers the mover, the landlord, and the staff. When that role is split, small decisions wait until move night.

Then get the building rules from both property managers in writing. Most Toronto office towers and many plazas control when a mover can work, which entrance and elevator can be used, and what insurance is required. These rules decide your date, not the other way round.

  • Lease end date at the old space, and the earliest access date at the new one.
  • Move hours each building allows. Many only release the dock after 6 pm or 9 pm.
  • Certificate of insurance requirements: certificate holder wording and minimum coverage.
  • Elevator booking rules, deposits, and floor and wall protection requirements.
  • Ask two or three movers to walk the space, not just quote from an email.

6 weeks out: decide what actually moves

A commercial move lives or dies on the item list. Either you give us exact counts of what is moving, or we come to the site and quote it in person — and for anything beyond a small office, the site visit is usually the better call. The reason is timing: commercial jobs almost always run inside a fixed window, so the crew has to be sized for the real scope up front. When the scope is accurate we staff the job to cover every step; when it is a guess, something gets discovered at 9pm on a Saturday.

Walk the floor and sort everything into four groups: moving, disposing, storing temporarily, and new items arriving at the new space. The storage group is the one people forget, and it changes the plan more than any other — a move that runs straight from A to B is a very different job from one that has to hold furniture for a week between leases.

  • Workstation, task chair, and filing cabinet counts. These three drive crew size.
  • Oversized pieces: boardroom tables, reception millwork, safes, anything with stone or glass.
  • Desks that come apart versus desks that move whole.
  • New furniture or racking being delivered to the new space. We install racking; we do not stock it. If you need racking as well as installation we can help you source and order it, but plan ahead — racking normally has about a month of lead time from order to delivery, so it needs to be raised well before your move date.

4 weeks out: book the building and the crew

Book the service elevator and loading dock at both addresses for the same window, then confirm the moving date with your mover. Send the certificate holder wording as soon as you have it. We issue certificates of insurance the same day, but building managers often want them several days ahead.

For budgeting, office moves are billed hourly for crew and truck together. With G&T that is $150 per hour for three movers with a 26 ft truck and $195 per hour for four, with a 2-hour minimum, plus a fuel and travel surcharge. Most office floors need three or four movers because of the chair and workstation count. Work outside normal hours carries an additional fee, which is confirmed when the window is quoted.

3 weeks out: settle IT, electrical, and installation

Decide who disconnects, moves, and reconnects the computers, and who handles the power and furniture at the new space. These are usually three different contractors, and the gaps between them are where the first morning goes wrong.

For most offices we recommend your own team disconnects the equipment and labels the cables and machines with stickers before move day — nobody knows your setup better, and it is the cheapest way to do it. We then wrap, transport, and place the hardware. If you would rather we handled disconnection, cable management, and packing, our IT crew does that work at $200 per hour.

If the new space needs desks assembled, cubicle panels installed, power run to workstations, or TVs and whiteboards mounted, it can be booked with the move. Our crew includes general installers and a licensed electrician with more than 10 years of experience, so the furniture and the power are done in the same visit.

2 weeks out: label and pack

Print the new floor plan, give each room or zone a colour, and put a matching sticker on every desk, cabinet, chair, box, and machine. On move night the crew places by colour without stopping to ask, and nothing gets stacked in a corridor and carried twice.

  • Staff pack their own desks and personal items into labelled boxes.
  • Empty filing cabinets, or confirm with your mover that they can travel loaded.
  • Back up servers and shared drives before anything is unplugged.
  • Photograph cable layouts behind each workstation and comms cabinet.
  • Tell staff and clients the last working day at the old address and the first at the new one.

Move week and move night

Reconfirm the elevator booking, security access, and dock time with both buildings 48 hours before the move. Make sure your coordinator and the mover’s lead have each other’s numbers.

Commercial jobs are led on site by the owner, not handed to a dispatcher. You have one direct number from the walk-through to the last piece placed, and someone answers it during the move — including at midnight. The crew is our own team, working to written rules: assigned roles, items inventoried and tagged before they leave the floor, nothing opened or set aside without the client’s say-so, and every area walked again before we leave. Your furniture, equipment, and records are treated as company assets, because that is what they are.

Before the crew leaves the old space, walk it together and check every room and storage closet. At the new space, walk it again with the floor plan in hand.

The first week after

Keep a short list of anything that needs adjusting: a desk in the wrong zone, a monitor arm, a shelf to rehang. Small corrections are much easier while the crew who did the move still remembers the layout. Return keys and fobs at the old address, collect your elevator deposits, and update your address with suppliers, clients, Google Business Profile, and Canada Post.